Client: Florida Department of Transportation (FDOT)
Location: Sarasota County, Florida
Project Type: Roadway Construction
Procurement Type: Contract – $12.3 Million

The Florida Department of Transportation (FDOT) has hired Bergeron Land Development (BLD) to improve more than two miles of SR 45 (US 41/Tamiami Trail) from Blackburn Points Road to Preymore Street in Sarasota County, Florida.

The enhancements will include a resurfaced roadway, wider pavement, improved drainage, updates to the intelligent transportation system (ITS), a northbound bridge replacement over North Creek, and a modification to the southbound bridge over North Creek.

Additionally, Bergeron Land Development will be responsible for milling, resurfacing, shoulder, sidewalk, driveway, curb and gutter reconstruction, signals, signing and pavement markings, lighting, traffic control, utility relocations, and other incidental construction.

The project, which began in January of 2020, is expected to be completed in June 2021.